Algorithms 2018,11, 18
priority, comparedwithotheroff-peak,mid-peak,andon-peakperiods. Thus, job i ispreferredtobe
processedacrossperiodsk,k+1,andk+2.Meanwhile, thecorrespondingelectricitycost isnamed
as cost1. However, if job i isprocessedwithinamid-peakperiod (i.e., thecorrespondingelectricity
cost isnamedas cost2), theelectricitycostmaybe lower.Hence, twopositionsareconsideredandan
illustration isgiven inFigure5. Let cA, cB, and cΓ represent theelectricitypricesofoff-peak,mid-peak,
andon-peakperiods, respectively. Toselect theoptimalposition, thekeyproperty1 isgivenas follows.
Figure4. IllustrationofCondition2.
Figure5. IllustrationofCondition3.
Property1. IfCondition3 is satisfiedandxi,k×(cB−cA)< xi,k+2×(cΓ−cB)holds, thebest choice for job i
is tobeprocessedwithinamid-peakperiod.
Proof. cost1= pi×(xi,k×cA+xi,k+1×cB+xi,k+2×cΓ)and cost2= pi× ti×cB. It is assumedthat
cost1> cost2, that is, cost1− cost2= pi× (xi,k×cA+xi,k+1×cB+xi,k+2×cΓ)− pi× ti× cB > 0.
Since ti=xi,k+xi,k+1+xi,k+2, it followsthat:
xi,k×(cB−cA)< xi,k+2×(cΓ−cB). (8)
Therefore,wheninequality (8)holds, job icanbedirectlyprocessedwithinamid-peakperiod.
Otherwise, job imustbeprocessedacrossperiodsk,k+1,andk+2. Thisends theproof.
Condition4:maxk∈A{Ik}>0anddk+2=0.
7
zurück zum
Buch Algorithms for Scheduling Problems"
Algorithms for Scheduling Problems
- Titel
- Algorithms for Scheduling Problems
- Autoren
- Frank Werner
- Larysa Burtseva
- Yuri Sotskov
- Herausgeber
- MDPI
- Ort
- Basel
- Datum
- 2018
- Sprache
- englisch
- Lizenz
- CC BY 4.0
- ISBN
- 978-3-03897-120-7
- Abmessungen
- 17.0 x 24.4 cm
- Seiten
- 212
- Schlagwörter
- Scheduling Problems in Logistics, Transport, Timetabling, Sports, Healthcare, Engineering, Energy Management
- Kategorien
- Informatik
- Technik