Seite - 76 - in Book of Full Papers - Symposium Hydro Engineering
Bild der Seite - 76 -
Text der Seite - 76 -
3.2. DESIGN APPROACHES
3.2.1. General Design Approach
Design work was completed by forming multi-disciplined sub-teams
assigned to specific design tasks, such as determining slope stabilization
methods, excavation depths, foundation objectives and treatments, underdrain
designs, structural concrete designs, RCC designs, and secant pile wall designs.
Leads and members of the sub-teams were organized beginning on March 6.
Eventually, over 100 professionals were involved in developing over 50 design
technical memorandums and contract plans and specifications. The work for the
preliminary designs was generally completed in Sacramento, with final designs
being completed by moving design team members to work on-site in Oroville.
This latter work was facilitated by mobilizing over a dozen portable trailers with
communication and computer equipment to a large parking area adjacent to the
Emergency Spillway. This allowed the design groups to be co-located with the
contractor’s (Kiewit’s) forces and to be on-site as the construction work was being
done. This also helped obtain expedited dam safety regulatory approval as the
designs were being finalized and the construction work was being completed, as
dam safety regulatory staff (FERC, DSOD) were provided temporary office space
in the trailers.
3.2.2. Geologic Investigations
During the original design, boreholes had been completed along the FCO
Spillway chute alignment and along the monoliths/weir sections of the Emergency
Spillway. There were also very detailed geologic maps of the FCO Spillway
chute and the monolith foundations completed during original construction, but
relatively little detailed geologic information was available on the Emergency
Spillway area downstream of the monoliths/weir sections. Geologic
investigations carried out in 2017 for the OER are described in detail in a
companion paper [2]. The 2017 geologic explorations included the use of 10 drill
rigs to complete over 104 new borings, install 26 piezometers, and install 15
inclinometers, all by the end of July 2017. In addition, 22 seismic refraction lines
were completed, and extensive geologic mapping of exposed rock was carried
out at both spillways.
The geologic investigations confirmed that the rock foundation at both
spillways consisted generally of amphibolite with varying degrees of weathering.
The degree of weathering ranged from intensely weathered or decomposed to
fresh, with most of the surface exposures consisting of moderately-weathered
rock. There were also numerous shears across both spillways, which
significantly contributed to both slope instability and erosion problems. Along the
FCO Spillway chute alignment, the vast majority of the intensely-weathered rock
was found at the two scour holes, with almost all of this original foundation
76
Book of Full Papers
Symposium Hydro Engineering
- Titel
- Book of Full Papers
- Untertitel
- Symposium Hydro Engineering
- Autor
- Gerald Zenz
- Verlag
- Verlag der Technischen Universität Graz
- Ort
- Graz
- Datum
- 2018
- Sprache
- englisch
- Lizenz
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Abmessungen
- 20.9 x 29.6 cm
- Seiten
- 2724
- Schlagwörter
- Hydro, Engineering, Climate Changes
- Kategorien
- International
- Naturwissenschaften Physik
- Technik