Seite - 81 - in Book of Full Papers - Symposium Hydro Engineering
Bild der Seite - 81 -
Text der Seite - 81 -
Faiz Makdisi, Ph.D., P.E., D.GE
Paul Schweiger, P.E., P.Eng, CFM
The Board of Consultants held their first meeting on March 1-3, 2017, with
the Spillway Recovery Team and dam safety regulators. Between March and
December 2017, the Board of Consultants met 14 times to review the designs
and to inspect construction in the field. The Board of Consultants completed
written reports following each meeting, providing comments and
recommendations to the Spillway Recovery Team, DSOD, and FERC, which
DWR then made available to the media and the general public.
OER also participated in a Risk Assessment Workshop conducted by the
United States Army Corps of Engineers in April 2017 and in a Potential Failure
Mode Analysis workshop in May 2017 conducted by DWR. These two
workshops focused on the safety of the FCO Spillway chute and the Emergency
Spillway.
5. LAKE OROVILLE OPERATIONS
Following the 2017 incident, DWR used the damaged FCO Spillway chute
intermittently between February and May 19, 2017, to pass reservoir inflows to
avoid using the unreliable Emergency Spillway. On May 12, DWR completed a
Near-Term Lake Oroville Operations Plan to support the final 2017 closure of the
spillway (FCO) gates in the second half of May, and to use the Hyatt Powerplant
releases to lower the reservoir to Elevation 214 m (700 ft) by November 1, 2017.
The objective of this operations plan was to minimize the likelihood of using either
spillway during the rest of the 2017 construction season, and to also minimize the
need for using the Emergency Spillway at all during the 2017-2018 Winter Flood
Season.
On October 16, 2017, DWR completed a Lake Oroville 2017/2018 Flood
Control Season Operations Plan targeted to limit flows on the FCO Spillway
chute and to prevent any flow through the Emergency Spillway. The 2017/2018
Plan was based on hydrologic and hydraulic analyses using historical
precipitation, snowpack, and reservoir data. It was also developed to balance the
competing needs of dam safety versus downstream flood safety. The 2017/2018
Plan incorporates a low initial reservoir elevation target to be held during the
Winter Flood Season and uses reservoir set points where increasing releases
would be made from the Hyatt Powerplant and the FCO Spillway chute to avoid
the use of the Emergency Spillway. The 2017/2018 Plan allows the reservoir to
pass the Standard Project Flood without releases on the Emergency Spillway and
without a discharge greater than 2800 m3/s (100,000 ft3/s) on the FCO Spillway
chute.
81
Book of Full Papers
Symposium Hydro Engineering
- Titel
- Book of Full Papers
- Untertitel
- Symposium Hydro Engineering
- Autor
- Gerald Zenz
- Verlag
- Verlag der Technischen Universität Graz
- Ort
- Graz
- Datum
- 2018
- Sprache
- englisch
- Lizenz
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Abmessungen
- 20.9 x 29.6 cm
- Seiten
- 2724
- Schlagwörter
- Hydro, Engineering, Climate Changes
- Kategorien
- International
- Naturwissenschaften Physik
- Technik