6. MEETING THE SCHEDULE
During the height of the 2017 construction season, the contractor (Kiewit)
had as many as 750 craft workers on site. During this season, the following work
was completed on the FCO Spillway chute before the November 1, 2017,
deadline:
320,000 m3 (420,000 yd3) of excavation
265,000 m3 (347,000 yd3) of RCC construction
234 structural-concrete slabs and 78 reinforced-concrete walls
constructed
32000 m3 (42,000 yd3) of leveling concrete constructed
23000 m3 (30,000 yd3) of structural concrete constructed
The progress of the work on the FCO Spillway chute is illustrated in Fig. 10,
and the pertinent events for OER are highlighted in Table 3. Final placement of
2017 concrete on the FCO Spillway chute was made on November 1, 2017 (see
Fig. 10), thus meeting the most important goal for the project.
Fig. 10 Aerial views of construction on FCO Spillway chute between May and
November 2017
Table 3
Pertinent Events in Oroville Emergency Recovery (OER)
2017
Date No. of
Days Event
Feb. 7 0 Initiation of Oroville Dam Spillway Incident
Feb. 12 5 Emergency declared, downstream areas evacuated
Feb. 23 16 OER Framework adopted
Mar. 1-3 22-24 First meeting of Board of Consultants
Mar. 6 27 OER leads organized, alternatives workshop
Mar. 15 36 Forensic Investigation Team selected
82
Book of Full Papers
Symposium Hydro Engineering
- Titel
- Book of Full Papers
- Untertitel
- Symposium Hydro Engineering
- Autor
- Gerald Zenz
- Verlag
- Verlag der Technischen Universität Graz
- Ort
- Graz
- Datum
- 2018
- Sprache
- englisch
- Lizenz
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Abmessungen
- 20.9 x 29.6 cm
- Seiten
- 2724
- Schlagwörter
- Hydro, Engineering, Climate Changes
- Kategorien
- International
- Naturwissenschaften Physik
- Technik