Seite - 512 - in Book of Full Papers - Symposium Hydro Engineering
Bild der Seite - 512 -
Text der Seite - 512 -
from flooding. However, it is not just a question of making the platform at a high
level, because the platform is being constructed on unimproved soils. The weight
of the platform and equipment must be supported by the unimproved soils before
the deep mixing soil improvement can be executed to make the suitable
foundation for the closure dike. There is a delicate balance between making the
platform high enough for safety against flash floods and low enough such that the
total weight of the platform and equipment can be supported by the unimproved
soils.
In the case of the Wonogiri reservoir that delicate balance resulted in a
platform consisting of two parts. First, primary embankment (varying thickness
but approximately 1 m) is placed up to Elevation 132. Second, the primary
embankment is overtopped with a constant 1 m thick layer of soil cement up to
Elevation 133. The DMSI columns will to be drilled thought the soil cement. This
layer of soil cement not only formed a firm platform but also acts to tie the
columns together to limit their horizontal displacements at the tops of the
columns.
Figure 7.
Typical Section of Primary Embankment and Soil Cement
The average existing ground elevation of the soft reservoir deposits was
around Elevation 131 and the construction window was assumed to start when
reservoir levels fell below that level. Therefore, the first year construction was to
consist of the following steps:
Step 1: After the reservoir level drops the soft deposits were left to dry
sufficiently enough to support equipment. Fortunately the construction window
corresponds to the normal dry season with strong warm dry winds occur across
the reservoir to aid in the drying. While waiting for the drying, clearing and
grubbing of the soils was manually executed. When the soils had dried
sufficiently to support the load of swamp-track bulldozers the area was then
stripped. Since the reservoir deposits were not entirely even, the area was
treated by zones corresponding to vary general levels. For the main Closure Dike
the area was divided into 7 zones as shown below:
512
Book of Full Papers
Symposium Hydro Engineering
- Titel
- Book of Full Papers
- Untertitel
- Symposium Hydro Engineering
- Autor
- Gerald Zenz
- Verlag
- Verlag der Technischen Universität Graz
- Ort
- Graz
- Datum
- 2018
- Sprache
- englisch
- Lizenz
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Abmessungen
- 20.9 x 29.6 cm
- Seiten
- 2724
- Schlagwörter
- Hydro, Engineering, Climate Changes
- Kategorien
- International
- Naturwissenschaften Physik
- Technik