9. Component 9, Managing Dam Safety Problems, with its activities of: Issue
Management System; Managing Non-conformances; Managing Physical
Infrastructure Issues; Managing Dam Safety Deficiencies
The score is: at a good practice (level 3). Related to the dam safety
management issues, periodical and special maintenance have been
prepared annually, in addition, related to the problem of dam safety, routine
visual inspection and monitoring of the safety parameters of the dam were
conducted by DMU staff and implemented well. DMU has set up a reliable
safety management of dam through inventory, categorization, priority
setting, investigations, and asessment of the dam safey issues.
10. Component 10, Emergency Preparedness, with its activities of: Hazard and
Consequence Identification; Owner Emergency Preparedness Plans;
Relationship with Community and External Agencies: Tests and Exercises
The score is: at a good practice (level 3), in relation to emergency
preparedness, DMU of Bengawan Solo RBO has prepared an Emergency
Action Plan though not yet for all dam, so that DMU of Bengawan Solo
RBO may increase the awareness in identification of hazard and
consequences potential failure of the dam and planning to respond to the
incidents that may cause failure of the dam. This includes preparation of
the plan for the state of emergency, build external relations and testing and
training emergency situations including the simulation for the state of
emergency in cooperation with the local government through Regional
Disaster Management Authority.
3.2. Review and Discussion
The maturity matrices were launched in early 2017 and followed with two
subsequent workshops in Batam (May 11-12, 2017) and in Semarang (July 17-
20, 2017). The result of the self-assessment above showed the acceptance of
DMU Bengawan Solo RBO to the maturity matrices is promising. The scoring of
each activity with its line item descriptions require understanding the nature of
the component, activity and also broader context of dam safety management as
well as dam safety standards and guidelines. Fortunately the DMU of Bengawan
Solo has sufficient competence human resources, so it is helpful in expediting the
familiarity to the application of such maturity matrix for evaluating dam safety
program.
Yet the objective of such assessment has to be achieved, in order to reach
further achievement and to expedite the scoring supporting its assessment result
with document as an evidence to facilitate scoring justification may also be
necessary. The assessment result and its descriptions is a good start to
demonstrate the anticipation of the DMU.
DMU as units that manage dams become vital objects on the application of
self-assessment using dam safety program maturity matrix to see their own
performance in running the program. Such assessment is conducted in
accordance with of the dam safety management based on the applicable rules
1160
Book of Full Papers
Symposium Hydro Engineering
- Titel
- Book of Full Papers
- Untertitel
- Symposium Hydro Engineering
- Autor
- Gerald Zenz
- Verlag
- Verlag der Technischen Universität Graz
- Ort
- Graz
- Datum
- 2018
- Sprache
- englisch
- Lizenz
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Abmessungen
- 20.9 x 29.6 cm
- Seiten
- 2724
- Schlagwörter
- Hydro, Engineering, Climate Changes
- Kategorien
- International
- Naturwissenschaften Physik
- Technik