be installed at the upstream face of the dam. In design phase, the reservoir level
is designed to be controlled at the Elevation 158.24. The contractor suggested
that the reservoir level shall be lower more 10 m. Then, the layout of rehabilitation
is shown in Fig. 5. The shadow part will be poured by SPUC.
Fig. 5
Layout of rehabiliation by SPUC of Wanyao dam
Two mix of SPUC are suggested, listed in Table 1.
Table 1
Mix suggested
No. 1 2
Requirement C25W8F100 C25W8F100
Cement, kg/m3 407 407
Fly Ash, kg/m3 128 128
Water, kg/m3 172 172
Sand, kg/m3 812 812
Coarse Aggregate, kg/m3 827 827
Superplasticizer, kg/m3 6.5 9.0
Slump, mm 450 750
Slump Flow, mm 260 280
V-Funnel, s 3.5 1.38
Air Content, % 4.4 4.4
SPUC will be mixed at the mixer plant at the dam crest and casted via a
funnel fixed at the crest and a tremie into the workspace underwater. UPA will be
diluted and casted into the water prior to the pouring of concrete same as other
projects. The photo of the dam and the cast plan is shown in Fig. 6. The width of
each block is 34 m and divided into 2 sub-block. 5 casting point will be set for each
sub-block since the distance between two casting points is designed as 5 m.
Construction of SPUC will start in the spring of 2018.
Shadow part will be
poured by SPUC
1181
Book of Full Papers
Symposium Hydro Engineering
- Titel
- Book of Full Papers
- Untertitel
- Symposium Hydro Engineering
- Autor
- Gerald Zenz
- Verlag
- Verlag der Technischen Universität Graz
- Ort
- Graz
- Datum
- 2018
- Sprache
- englisch
- Lizenz
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Abmessungen
- 20.9 x 29.6 cm
- Seiten
- 2724
- Schlagwörter
- Hydro, Engineering, Climate Changes
- Kategorien
- International
- Naturwissenschaften Physik
- Technik