a several recommendation for the urgent maintenance of Keuliling Dam as shown
in the the following table 1.
Table 1. The Urgent of Operation and Maintenances Work of
Keuliling Dam
No Building and
Instruments Recent Condition Recommendation
1. Data Logger
(Instrumentation
house) The automatic
instrumentation reading
is in a damaged state
(data can not be read)
caused by lightning that
interfere with the
program. Need an immediate
reparation.
2. Vibrating wire
piezometer - Readings were done
manually on the house -
- Vibrating wire
piezometer in the body of
the main dam, the data
was readable for 5 of 18
points attached to the
main dam
- Not perfectly
accessible digitally on
the instrument house Need a calibration data
3. Inclinometer -The box cover is in
broken condition
-The inclinometer
equipment need to be
calibrated and the
battery should be
renewed The close box need to be
repaired immediately to
avoid from further
destruction which may
result in the error reading
of inclinometer and
the device needs to be
re-calibrated
4. Openstandpipe
Piezometer (OP) The box cover of
Openstandpipe is
damage The close box need to be
fixed to avoid the
clogged pipe holes.
5. The inundation area There are fish cages Control and prohibit the
activities of fish cages for
water quality and
sediment in the reservoir.
1321
Book of Full Papers
Symposium Hydro Engineering
- Titel
- Book of Full Papers
- Untertitel
- Symposium Hydro Engineering
- Autor
- Gerald Zenz
- Verlag
- Verlag der Technischen Universität Graz
- Ort
- Graz
- Datum
- 2018
- Sprache
- englisch
- Lizenz
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Abmessungen
- 20.9 x 29.6 cm
- Seiten
- 2724
- Schlagwörter
- Hydro, Engineering, Climate Changes
- Kategorien
- International
- Naturwissenschaften Physik
- Technik