2. HISTORICAL OVERVIEW
The historical development of ejector power plants goes back to the early
20th century. The first experimental investigations took place in 1905. Mosonyi [1]
cites Herschel as having applied special solutions as early as 1909. There were
three main types of construction here.
excess discharge is jetted into the draft tube through the ejector
channel
excess discharge is released through overfall spillways around the
draft tube
excess discharge is released through spillway chute over the draft tube
The heyday for ejector power plants was the 1930s. Especially in the Soviet
Union, but also in Europe and the United States, plants of various kinds were
planned and built (Hodenpyl power station USA, Kembs power plant on the
Rhine, and Alcona power station USA). Hydropower plants utilizing the ejector
effect to reduce the loss of drop height in flood conditions by lowering the water
level in the tail race were examined in greater detail, for example, in the early
1950s on the basis of built facilities in the then Soviet Union [2].
1365
Book of Full Papers
Symposium Hydro Engineering
- Titel
- Book of Full Papers
- Untertitel
- Symposium Hydro Engineering
- Autor
- Gerald Zenz
- Verlag
- Verlag der Technischen Universität Graz
- Ort
- Graz
- Datum
- 2018
- Sprache
- englisch
- Lizenz
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Abmessungen
- 20.9 x 29.6 cm
- Seiten
- 2724
- Schlagwörter
- Hydro, Engineering, Climate Changes
- Kategorien
- International
- Naturwissenschaften Physik
- Technik