3.2. CONSTRUCTION
Each Contractor has its own particular mentality and preferences for means
and methods, as well as for equipment. Each project’s construction details
must therefore be evaluated on this basis, with the prime concern being the
safety of the dam during construction.
A proper, stable, working platform (concreted if possible) is essential for a
host of reasons, ranging from personnel safety to enhancing productivity.
Some cutoff walls involve extensive pregrouting such as in the “Composite
Wall” concept [6]. Such grouting must be conducted by an experienced and
knowledgeable Contractor who may not necessarily be the same business
entity as the cutoff wall Contractor. Insufficient or ineffective grouting may
create dire problems to subsequent cutoff wall quality and schedule.
“Technique Demonstration Areas” – thoroughly assessed – are invariably of
great value to all the project’s stakeholders.
Time is well spent up front in building high quality, weatherproofed bentonite
and concrete storage and batching facilities, and maintenance shops.
Development of mix designs and their approval by the Owner should not be
allowed to negatively impact schedule and should be given high priority
during the site mobilization phase.
All preconstruction permits, etc., must be in place prior to site mobilization.
Ensure that all equipment is maintained regularly, and that all instrumentation
is frequently recalibrated (if necessary).
Individual cutoff wall elements, be they diaphragm wall panels, or secant
piles, should be sized to minimize the number of inter-element joints,
consistent, however, with dam safety concerns.
3.3. QA/QC AND VERIFICATION
Details must be linked directly to the design intent and the project
specifications, regulatory requirements, and to the actual construction
techniques adopted by the Contractor.
Key elements promoting success include:
Clear and complete contract specifications and drawings;
Appropriate organizational structure and qualified personnel;
Good communication protocols;
Cooperation from all parties (Owner, Engineers and Contractors);
Diligent implementation of the Quality Plan.
A comprehensive, formal Quality Control Implementation Plan is essential,
and the effort needed for the drafting and implementation of this Plan should
not be underestimated by the Contractor. This project-specific plan must
address, as a minimum:
Site organization charts showing responsibilities, lines of communication
and levels of authority of project personnel from all stakeholders;
1630
Book of Full Papers
Symposium Hydro Engineering
- Titel
- Book of Full Papers
- Untertitel
- Symposium Hydro Engineering
- Autor
- Gerald Zenz
- Verlag
- Verlag der Technischen Universität Graz
- Ort
- Graz
- Datum
- 2018
- Sprache
- englisch
- Lizenz
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Abmessungen
- 20.9 x 29.6 cm
- Seiten
- 2724
- Schlagwörter
- Hydro, Engineering, Climate Changes
- Kategorien
- International
- Naturwissenschaften Physik
- Technik