5. TEMPERATURE CONTROL EFFECTS OF P.LH DAM CONCRETE
In the procedure of P.LH concrete construction, the intelligent temperature
system, such as pre-cooled concrete, intelligent water supply and surface heat
preservation are applied.
The secondary air-cooling plus mixing with ice are used in batching system
of concrete and the concrete temperature at outlet of the batching system will be
adjusted dynamically in accordance with the ambient and concrete temperature
poured. Simultaneously, full close heat preservation dumper are adopted for
transportation to improve efficiency and accelerate concrete pouring so as to
reduce temperature recovery during transportation.
The layer covering time in concrete placement shall be controlled within 4h
to decrease temperature recovery, and 2cm thick canvas quilt for heat preservation
shall cover to prevent the concrete from temperature flowed backward and air-dry
of the surface aggregate. 2h before concrete pouring, mist will sprayed to decrease
temperature while temperature in the concrete pouring area in sunshine is over
23℃( or greater than 28℃ without sunshine). After concrete finished, mist spray
shall be continued for curing and it will be changed to spun spray for curing to form
flowing water film. In transverse joint and upstream and downstream surface,
flower pipe is adopted for curing. 4cm thick urethane foam is coat over the
upstream surface and 3cm thick polystyrene extrusion plate is pasted over the
downstream surface for annual heat preservation.
In order to guarantee the temperature less than the presettings during water
cooling, the Max. temperature will be preset as 2℃ according to Max. Temperature
to adjust water temperature and flow, and 0.5℃/d temperature decrease shall be
controlled after the temperature reaches peak value. The temperature control
principle is small temperature difference and early cooling. The cooling pipe is
always full of water after pipeline laid in the concrete placement area, and the
cooling water will be changed into intelligent cooling water control system directly
after concrete finished.
The result measured shows: it takes 5~10 days to the Max. value in low
temperature season. it takes 4~8 days to the Max.value in high temperature
season. The average temperature of concrete in the placement area shall be
controlled in 24.1℃~26.4℃ which is lower than 27℃ designed as the Max. allowable
temperature.There is no temperature crack fund till now.
It is known from the site practice that the Max. temperature of concrete can
be more easily controll while adoption of P.LH concrete and the temperature control
measures maybe be still optimized.
1687
Book of Full Papers
Symposium Hydro Engineering
- Titel
- Book of Full Papers
- Untertitel
- Symposium Hydro Engineering
- Autor
- Gerald Zenz
- Verlag
- Verlag der Technischen Universität Graz
- Ort
- Graz
- Datum
- 2018
- Sprache
- englisch
- Lizenz
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Abmessungen
- 20.9 x 29.6 cm
- Seiten
- 2724
- Schlagwörter
- Hydro, Engineering, Climate Changes
- Kategorien
- International
- Naturwissenschaften Physik
- Technik