collars. A concrete encasement or cradle around or under conduit
penetrations through earthen/rockfill embankments allow for better
compaction of earthfill/rockfill.
The first filling of a reservoir should be planned, controlled and monitored.
Treatment of fractured foundation rock for embankment parts of composite
dams is important to prevent internal erosion of embankment material that
is in contact with the foundation.
Stability of the dam foundation and other geologic features must be
considered during composite dam design.
The design engineer should be involved in the construction phase of
composite dam projects.
High and significant hazard rockfill parts of composite dams should have
internal filter and seepage collection systems.
External independent peer review of designs and decisions is an effective
means of providing quality assurance and reducing the risk associated with
design oversights and deficiencies.
Local experience must be consulted and considered for composite dam
solutions for better effectiveness and local compliance.
PMF magnitude floods do occur. High and significant hazard dams should
be designed to pass an appropriate design flood.
Composite dams need an operable means of drawing down the reservoir.
Access shall be provided and available at all times for the inspection and
routine maintenance of gates and other mechanical systems at composite
dams.
Composite dams and grouting galleries located in areas of potential seismic
activity need to be evaluated for liquefaction, cracking, potential fault
offsets, deformations, and settlement due to seismic loads.
Alkali-aggregate reactions (AAR) can cause serious concrete deterioration
and other problems at concrete/RCC parts of composite dams.
Most concrete/RCC parts of composite dam failures are the result of
foundation stability problems.
Concrete/RCC parts of composite dams founded on bedrock require
detailed corroborating subsurface investigations and testing of rock
properties.
Outlet works and pressurized conduits in composite dams should be
provided with a means for upstream closure.
Composite dams built from or on loose granular soil can be susceptible to
liquefaction of the foundation material.
Settlement of rockfill parts of a composite dam can reduce freeboard and
increase the risk for overtopping. Composite dams should be designed with
allowances for settlement.
For high and significant hazard composite dams, elements that are critical
for the safe operation of the dam should all be engineered.
As for the traditional dams, internal erosion can take decades to progress
in composite dams.
Karstic foundations are difficult to treat and can cause internal erosion
issues and require special attention.
1936
Book of Full Papers
Symposium Hydro Engineering
- Titel
- Book of Full Papers
- Untertitel
- Symposium Hydro Engineering
- Autor
- Gerald Zenz
- Verlag
- Verlag der Technischen Universität Graz
- Ort
- Graz
- Datum
- 2018
- Sprache
- englisch
- Lizenz
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Abmessungen
- 20.9 x 29.6 cm
- Seiten
- 2724
- Schlagwörter
- Hydro, Engineering, Climate Changes
- Kategorien
- International
- Naturwissenschaften Physik
- Technik