cavern is 1700m above sea level. The Obervermuntwerk II will utilize the existing
water capacities of the Vermunt and Silvretta reservoir to generate peak and
balancing energy. The water from the Silvretta reservoir feeds the underground
powerhouse cavern through the 2800m long Silvretta high-pressure tunnel. The
maximum overburden is roughly 1100m. Fig.1a shows an overview of the entire
project area. The Silvretta high-pressure tunnel is lined with pre-casted segmental
linings in the invert and an in-situ concrete shell. The last 600m of the Silvretta
tunnel are first lined with a thin steel shell and an interior concrete core ring (length
of 255m) followed by a thick-walled steel lining, which is designed to withstand the
external pressure.
The Vermunt reservoir acts as a storage reservoir for pumping mode and is
connected to the cavern with a 380m long tailwater tunnel. The length of the
powerhouse cavern is 125m, the width is 25m and the average height is 33m. The
powerhouse consists of two ternary machine units with a capacity of 180MW and
two pumps of 180MW each. The turbines are designed to have a height between
240m and 310m. Fig. 1b shows a schematic plan view of the two caverns and Fig.
2 shows a detail of a typical cross section through the powerhouse cavern including
the anchor design and the different excavation levels. A detailed description of the
project and the design procedure can be found in Dich et al. [2].
Fig. 1
a) Project overview; b) Plan view of transformer and powerhouse cavern
3. ROCK CONDITIONS
All plant components of the Obervermuntwerk II lie in the Silvretta crystalline.
This formation consists mostly of granite gneisses, amphibolites, slate gneisses
and mica schist, with the latter being encountered at the intake structure and the
gate chamber. The Silvretta tunnel, the pressure tunnel and the tailrace tunnel lie
completely in the granite gneiss, as can be seen in Fig. 2. The granite gneisses
generally show low to moderate rock mass permeability. A detailed description of
the geological conditions is given in Dich et al. [2].
2095
Book of Full Papers
Symposium Hydro Engineering
- Titel
- Book of Full Papers
- Untertitel
- Symposium Hydro Engineering
- Autor
- Gerald Zenz
- Verlag
- Verlag der Technischen Universität Graz
- Ort
- Graz
- Datum
- 2018
- Sprache
- englisch
- Lizenz
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Abmessungen
- 20.9 x 29.6 cm
- Seiten
- 2724
- Schlagwörter
- Hydro, Engineering, Climate Changes
- Kategorien
- International
- Naturwissenschaften Physik
- Technik