The only surprise was in the Silvretta tunnel, with a significant increased water
ingress (peak of about 120l/s) along a length of about 200m. Consequently, the
round length was reduced from 3.0m to 1.5m and the instrumentation of the
monitoring system was increased.
In the intake tunnel and the Silvretta tunnel, which are lined with cost
concrete inner lining, the formwork striking time was ten hours. At the time point of
striking, an average early strength of 6MPa was reached, with a specified minimum
strength of 2MPa. The concrete was then cured to avoid shrinkage cracking.
Concreter repairs were only required to a very small extent. In the sections with
thin-walled steel lining, the external ring was backfilled with concrete after installing
the 14m long pipe sections. The formwork unit for the concreting of the support
ring followed offset at a spacing of 7m. Due to a coordinated sequence, the works
proceeded without delays. No concrete repairs were necessary.
The thin-walled steel lining had to be secured against floating in order to
ensure its circularity. This provided a binding band and two invert ties in the middle
and four invert ties at the ends of each 14m long pipe section. The pipe section
lengths for the thick-walled steel lining were generally 10.5m. After attachment and
quality controls, each pipe section was concreted. The backfill concreting of the
turbine feed and pump riser pipes was carried out in a filled state under pressure
in order to achieve a pre-stressing in the longitudinal direction of the manifold.
SUMMARY
3D finite element analyses were performed in order to assess the
performance of the two main caverns of the PSHPP Obervermunt II. Of main
concern was the stress redistribution within the surrounding rock and the
settlement behaviour of the cavern powerhouse during the different excavation
phases. The computations predict 15 to 20mm of displacements at the crown of
the powerhouse cavern and show that next to the side tunnels stress
concentrations have to be expected.
The article provides also a brief overview of construction progress on the
major project pumped storage works Obervermuntwerk II. Both the geotechnical
design and the experience gained during the construction of selected sections is
discussed. The complexity of the project with the technical requirements for the
tunnel linings require some special measures, which are presented in detail.
Also described is the headrace system with the 2.4km long Silvretta
headrace tunnel, which is first lined with a non-reinforced in-situ concrete lining,
then with a thin-walled steel lining (including an inner in-situ concrete core ring)
and the last part is lined with a thick-walled steel lining. Both the Silvretta penstock
and the distributing conduit are designed with a thick-walled steel lining. The
decision where to use which of the four lining parts is based on a number of
constraints, namely the rock and steel parameters, the inner and outer pressure
and the minor principal stress in the surrounding rock mass.
2102
Book of Full Papers
Symposium Hydro Engineering
- Titel
- Book of Full Papers
- Untertitel
- Symposium Hydro Engineering
- Autor
- Gerald Zenz
- Verlag
- Verlag der Technischen Universität Graz
- Ort
- Graz
- Datum
- 2018
- Sprache
- englisch
- Lizenz
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Abmessungen
- 20.9 x 29.6 cm
- Seiten
- 2724
- Schlagwörter
- Hydro, Engineering, Climate Changes
- Kategorien
- International
- Naturwissenschaften Physik
- Technik