HOLLOW CONE VALVE (HCV) IR. H. DJUANDA DAM
AND MURI INDONESIA RECORD
Yudha Mediawan1), Angga Prawirakusuma, ST. MT2), Ir. Joko Mulyono, ME3),
Dwi Aryani Semadi, ST. SP14)
1) Kepala Balai Besar Wilayah Sungai Citarum
2) PPK OP III SDA BBWS Citarum
3) Jafung Teknik Pengairan Ahli Madya, Ahli Teknik Bendungan Besar – Utama
4) Kabid PJSA BBWS Cimanuk Cisanggarung, Ahli Teknik Bendungan Besar –
Madya
ABSTRACT
Construction of Ir. H. Djuanda Dam or better known as Jatiluhur dam which was
implemented from 1957 until 1967, this construction project called "Jatiluhur
Multipurpose Project" and after its completion was named as Juanda Dam and
Power Plant, after finished the name was changed to Juanda Dam and Power Plant
because remembering the role of Prime Indonesia's last minister that is Ir. H.
Djuanda. Basically Jatiluhur / Juanda Dam construction project is designed to
irrigate tens of thousands hectares farmland and fisheries, electricity for Java -
Bali lighting, main supplier of water for industry, raw water supply for capital city
and tourism. Currently Jatiluhur Dam/Juanda age have reach 50 years, pollution
and sedimentation become a worrying problem so that in 2012 there is great
inspection by ACE Pakistan JV consultant through Dam Operation Improvement
Safety Project (DOISP) obtained description of dam condition and facility
building has decreased function as in mechanical equipment that is hollow cone
valve. Referring to Decree of Public Works Minister Number 315/KPTS/M/2011
about Authority Delegation to General Director of Water Resources to regulate
operation of Saguling Dam, Cirata Dam and Jatiluhur Dam which main task is
monitoring and evaluation cascade dam by Balai Besar Wilayah Sungai Citarum
through Operation and Maintenance of Citarum Water Resources for doing
repair/replacement the mechanical equipment above.
Replacement of two hollow cone valve diameters of 3.85 m with material
(stainless steel) meets the same standard as Z5 CN 17-04 M in accordance with
asbuilt drawing on previous data. The making of this HCV has been awarded the
Indonesian Record Museum (MURI) which is work of nation's children, as well as
manufacture and installation of replacements process has been written simply.
There are several problems in the implementation that can be solved there are:
1. HCV manufacturing and auxiliary equipment (cantilever) are new in
Indonesia both from size and mounting method with mathematical models
only for model test.
2168
Book of Full Papers
Symposium Hydro Engineering
- Titel
- Book of Full Papers
- Untertitel
- Symposium Hydro Engineering
- Autor
- Gerald Zenz
- Verlag
- Verlag der Technischen Universität Graz
- Ort
- Graz
- Datum
- 2018
- Sprache
- englisch
- Lizenz
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Abmessungen
- 20.9 x 29.6 cm
- Seiten
- 2724
- Schlagwörter
- Hydro, Engineering, Climate Changes
- Kategorien
- International
- Naturwissenschaften Physik
- Technik