After the work of rail replacement and brushing flange then continued by
lowering new HCV using chain block and shifted trolly into approaching flange.
Flange bolts installation is doing with a firming load of ±610 kg for each bolt by
looking at digital scales.
Figure 4.17 Bolt Installation Process with Specified Load
5. COMMISIONING
5.1. COMMISIONING TEST
After Hollow Cone Valve is mounted, continuously with disassembly of
work desk tool, safety net and doing the Commissioning Test on June 12th, 2017.
Commissioning test is a part of final stage to try hydromechanical and
mechanical reliability of Hollow cone valve, in implementation of this test is
divided into two parts. Dry test is a test of HCV motion function without any load
with stop log concrete (check name to pjt) in closed position. This test only
checks the HCV motion when open and close 5% increments start from 0 until
100% and 100% to 0 position. Load Test is a test such as dry test but with
hydrostatic load which stop log concrete in opened position so that causing burden
to mounted HCV.
Figure 5.1 Commissioning Test
2177
Book of Full Papers
Symposium Hydro Engineering
- Titel
- Book of Full Papers
- Untertitel
- Symposium Hydro Engineering
- Autor
- Gerald Zenz
- Verlag
- Verlag der Technischen Universität Graz
- Ort
- Graz
- Datum
- 2018
- Sprache
- englisch
- Lizenz
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Abmessungen
- 20.9 x 29.6 cm
- Seiten
- 2724
- Schlagwörter
- Hydro, Engineering, Climate Changes
- Kategorien
- International
- Naturwissenschaften Physik
- Technik