Page - 57 - in Book of Full Papers - Symposium Hydro Engineering
Image of the Page - 57 -
Text of the Page - 57 -
developing “what if” scenarios and working to reinforce the decision-making
processes. Initially, erosion occurring downstream of the Emergency Spillway was
within expected levels. . However, on February 12, significant erosion of the rock
hillside was noted to be progressing more rapidly than anticipated to the point where
it was considered a threat to the Emergency Spillway. This situation prompted an
immediate meeting between the Butte County Sheriff, DWR’s Acting Director, OICT
management, DSOD, and FERC. Suggestions, such as increasing the FCO
Spillway release to 5949 m3/s (210,000 ft3/s) to stop flow over the Emergency
Spillway, had to be rejected since that would exceed downstream levee capacities,
causing flooding of downstream communities. Based on the best available data,
including the FCO Spillway’s current condition, Powerplant flooding potential, the
potential for erosion failure of the Emergency Spillway, and continual forecasts, the
DWR’s Acting Director agreed to increase FCO Spillway releases to 2832 m3/s
(100,000 ft3/s). With the flow through the FCO Spillway increased to 2832 m3/s
(100,000 ft3/s) February 12 at 1800 hours, the flow over the Emergency Spillway
stopped several hours later.
DWR maintained the FCO Spillway release at 2832 m3/s (100,000 ft3/s until
February 16. On February 16, the Lake Oroville water elevation dropped low enough
for the Butte County Sheriff to change the mandatory evacuation to an evacuation
warning, allowing an estimated 188,000 people to return to their homes and
businesses.
Emergency repairs were developed and implemented, using air and ground
resources. It was critical to repair the erosion damage below the Emergency
Spillway in case it had to be used again. These emergency repairs to the Emergency
Spillway consisted of filling erosion voids and armoring the ground surface. However,
they were viewed as temporary, based on limited information, planning, and design.
Fortunately, the Oroville Emergency Recovery team was onsite 24/7 and was able
to collect advance-planning data and information as the damaged area was being
backfilled and armored. This response effort was extremely large, yet simple in
approach and had no planned stopping point set. DWR Executive management, in
close coordination with DSOD and FERC, addressed terminating the Emergency
Spillway repairs based on available reservoir storage, forecast, and the amount of
completed temporary repair work.
57
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik