SETTING UP DREDGING AND SPOILBANK MANAGEMENT METHOD TO
RECOVERY HYDROPOWER PRODUCTIVITY OF SENGGURUH DAM
Aris Yhadhianto
Civil Engineer, JASA TIRTA I PUBLIC CORPORATION, INDONESIA
INDONESIA
Ulie Mospar Dewanto
Deputy of Operational II, JASA TIRTA I PUBLIC CORPORATION,
INDONESIA
ABSTRACT
Sengguruh dam located in Brantas River watershed, East Java, Indonesia
was completed in 1988. The objectives is for generating hydroelectric power plant
with installed capacity 2 x 14,5 mW produce of 91 million kWH per year. Located
at uppermost of the series dams in Brantas River Basin and therefore is utmost
suffered of sedimentation. Also, it prevents sediment comes to the Sutami which
is the biggest reservoir at down stream part. The inflow come from two main
rivers, namely Brantas River and Lesti River has a catchment area of 1.659 km2.
The condition currently declining due to the high rate of sedimentation. Based on
the echosounding result conducted in 2016, is known that effective capacity has
been reduced to 0,6 million m3, or approximately 24% of the initial conditions of
2,5 million m3 and electric generation has been reduced to 68,8 x 106 kWH. The
dredging activity has been done routine every year from year of 2001 with an
average dredging volume of 300,000 m3/year. Total achievement of the volume
of dredging result seems large, but it is not adequate. Based on the present
evaluation, particularly in the zone at front of hydropower intake (namely zone 1),
was in fact already quite critical because the sediment is getting closer. The zone
distance is about 100-200 m with the difference elevation from sediment surface
reaching 7-12 m above desired reference base elevations. On contrary, the
dredging has been done in the upstream area which is quite far away + 1,500-
2,000 m from zone 1 due to get close of spoilbank location. In order to sort out
the problem and to support President Joko Widodo's Government policy in
energy security, the dredging method in 2016 was changed. The innovation and
302
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik