The Project is being financed by International Finance Corporation (IFC), Asian
Development Bank (ADB), Korea Exim Bank (K-Exim), CDC Bank of UK and
Multilateral Development Bank of Netherland (FMO). The Project achieved
Financial Closing in October 2015 and set to achieve commercial operations by
August 2019 with 70% construction already completed. The Project is being
constructed by renowned consortium of Korean construction companies i.e.
Daelim Industrial and Lotte E&C and many international consultants/technical
advisors are collaborating at different levels including Mott McDonalds as
technical advisor of Lenders, MWH as Owners Engineer and Multi Consultant
(UK) as independent engineer.
Back in 2013 when KOEN decided to invest in Pakistan, the country had a
serious power crisis. Everyday millions were being affected by electricity
shortage up to six hours in urban areas and twelve hours in rural locations which
leads to slowing of productivity and hampering economic growth. KOEN believed
at that time that in a country, rich in water resources hydropower can have a
significant role in meeting future energy needs.
While acquiring the project KOEN was already very keen to focus on
environmental challenges in maintaining the rich ecology and diverse
environment specifically in view of already environmental sensitive location
where other than rest of the needful almost 128 households were to be resettled/
relocated.
The Project is also in compliance with International Finance Corporation (IFC)’s
Performance Standards and Asian Development Bank Safeguard Policy
Statements. To meet such requirements and to face the prospective challenges
from civil society, NGOs, Government and local communities, KOEN facilitated
Mira Power to adopt a comprehensive approach of sustainable development.
2. STEPS TOWARDS SUSTAINABLE DEVELOPMENT
To achieve sustainable development plan Mira Power has adopted flawless
strategy and devised following best possible plans:
ï‚· Biodiversity Action Plan
ï‚· Land Acquisition and Resettlement Plan
ï‚· Livelihood Restoration and CSR Plan
ï‚· Stakeholders Engagement Plan
ï‚· Sustainable Mining Plan
ï‚· Security Management Plan
ï‚· Construction E&S Management Plan
ï‚· Health and Safety Plan
656
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik