Page - 829 - in Book of Full Papers - Symposium Hydro Engineering
Image of the Page - 829 -
Text of the Page - 829 -
SUMMARY
The Mavčiče concrete gravity dam, part of the corresponding hydro-power
plant, was built on the Sava River, in Slovenia, in 1986. It has a maximum
structural height of 38.5 m, and the dam crest has a length of 149 m. The dam
structure consists of an erection bay, a machine hall, and two spillways, followed
by an embankment dam. Most of the dam is founded on permeable Quaternary
conglomerate bedrock, so that a cut-off grout curtain had to be constructed to a
depth of up to 60 m below the ground surface, where a layer of impermeable
Oligocene marine clay occurs. However, the erection bay, which is located on the
right bank of the dam, is founded on a layer of gravel backfill, up to about 25 m
thick, which lies on top of the conglomerate bedrock.
Long-term manual technical monitoring of the behaviour of the dam began
in 1986, and an automated monitoring system was established between 2003
and 2005. In general, the results of measurements and visual inspections did not
show any abnormalities. However, this was not the case for the erection bay
located on the top of the backfilled right bank of the dam, where the results of
measurements of vertical displacements showed increasing settlements. By
1999, i.e. over a period of 12 years, these settlements had increased to 22 mm.
The results of investigations, by drilling three research boreholes in 1993,
and another six such boreholes in 1996, indicated that the settlements were the
consequence of the secondary consolidation of the backfill, and probable also
due to scouring of fine material from the backfill. Due to the resulting differential
settlements, the crane rail which connects the erection bay to the machine hall,
as well as the crane rail which is located along the crest of the dam, became non-
functional, and needed height corrections. For this reason rehabilitation works of
the backfill and of the substratum of the right bank of the dam were performed
between September 1999 and August 2000, using 50 m long grouted boreholes.
This grouting was performed using a combination of water reactive polyurethane
and a cement-bentonite mixture. Measurements performed since than have
shown that the settlement rate has slowed down slightly (by 2017, i.e. over the
last 17 years, the settlements had increased by up to 8 mm), but from the point of
view of the operation of the two crane rails the settlement process needed to be
stopped. Additional investigations, involving the drilling of two research
boreholes, as well as appropriate laboratory and field measurements, were
performed between November 2015 and March 2016. According to the results of
these most recent investigations, the newer settlements were the consequence of
additional scouring of fine material from the backfill.
In order to achieve a final solution to the problem of the subsidence of the
erection bay, additional rehabilitation works of the backfill and substratum of the
right bank of the dam, by grouting the permeable zones, would be needed in
order to stop both the scouring of fine material from the backfill, as well as any
internal erosion of the cavernous conglomerate at the base of the backfill. The
latter concerns the long-term stability of the right bank of the dam with potentially
serious results.
829
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik