COMMISSION INTERNATIONALE
DES GRANDS BARRAGES
-------
VINGT-SIXIÈME CONGRÈS DES
GRANDS BARRAGES
Autriche, juillet 2018
-------
HYDRAULIC ASSESSMENT OF TUNNELS
Balkrishna Shankar CHAVAN,
Scientist-D, Central Water and Power Research Station, Pune
India
1. INTRODUCTION
A river diversion tunnel is used to divert river water during construction of a project.
Once construction is over, diversion tunnel is plugged before initiating storage of
water consequently tunnel part becomes redundant. No universally accepted
standards are available for design of temporary structures like coffer dams and
diversion tunnels. Tunnel construction has high costs and usually adopted when
other solutions are unfeasible. Length of tunnel is kept minimum as possible. To
minimize the project cost, part of diversion tunnel can be reused for depletion of
reservoir storage. There are instances where part of river diversion tunnels have
been used as depletion tunnel after construction of dam is completed. In India
projects such as Yamuna, Doyang, Nagarjunsagar, Salal have successfully used
the concept of multipurpose tunnel for diversion of river flow and depletion of
reservoir. Hydraulic design associated with such tunnels has to function
satisfactorily for high discharge at low head during construction and also high head
1530
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik