annulus grout is lost to the formation. This situation lends to defects or
incomplete filling of the annulus. These defects can permit direct connection of
embankment materials to the foundation and/or connection of grouting fluids up
into the embankment during the drilling and grouting operations at lower depths.
Both situations are serious dam safety issues.
Arguments for the cessation of annulus grout include avoiding potential
hydrofracture of soft embankment or foundation soils above the bedrock.
However, it should be noted that most standpipes are drilled and installed into the
top of rock immediately below the embankment. This zone of rock is often the
most permeable and the zone of rock that most likely led to the need for the
remediation being conducted. It is much more likely that any grout take during
standpipe installation is flowing into the bedrock or weathered features of the rock
(or an alluvium layer remnant immediately above rock) rather than into
embankment materials. Bedrock that is being treated during standpipe installation
should be viewed as part of the treatment program and should be grouted to
refusal just as any other standard grout stage.
In order to adequately backfill and install standpipes, the designer has two
options. The first option is to backfill the entire annulus in one complete
operation, adding grout as needed and maintaining a continuous head of grout in
the annulus at all times until the grout comes to surface and remains at the
surface. The second option is recommended for areas of suspected weak
embankment soils or zones in which the designer wishes to avoid potential
hydrofacture. This option involves the use of Multi-Port Sleeve Pipe (MPSP) with
a barrier bag that is inflated with grout at the embankment/foundation interface.
The barrier bag hydraulically separates the embankment from the bedrock
foundation with the use of a barrier bag. (Figure 1).
Fig. 1
Separation of embankment and foundation
Step 2: Move Packer
Systems to Upper Port and
Grout Annulus to Surface Step 3: Withdraw Sonic Casing,
Topping Up if Necessary
Step 1: Inflate Barrier System at
Top of Rock Using Double
Packer and Sleeve Port Pipe
Step 4: Insert Single Packer
and Grout Interface
Through Lower Port
1616
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik