The annulus can then be filled through a port in the standpipe above the
barrier bag, while the critical interface and bedrock immediately below the bag
can be treated and evaluated as a separate grouting stage. Either option
involves the continuous and uninterrupted backfilling of the hole annulus within
the embankment to the top of the hole. Use of the barrier bag to separate and
isolate the embankment from the foundation is the only method that verifies that
hydrofracturing of the embankment is not occurring. Grout coming to the surface
around the outside of a standpipe that was incompletely filled during installation
is not evidence of hydrofracturing: it is evidence that the installation method is
inappropriate and has created a dam safety concern.
On a similar note, use of very low excess pressures or even gravity head
during water testing and grouting due to fears of hydraulic fracturing in advance
of cutoff wall construction is misguided. Again, if a zone of the embankment or
gouge within rock defects is susceptible to fracture or erosion under low
pressures, then one needs to know this prior to excavating the cutoff wall. On
one recent project, the allowable water pressures during testing were so low that
the headloss through the delivery pipe was not exceeded when flow started and
zones with zero water take subsequently consumed very large quantities of grout
during pressure grouting. If these zones had not been grouted under pressure
due to the low or zero water take and had been backfilled in stages in
accordance with the requirements above, then a future large slurry loss during
cutoff wall excavation would have been the inevitable result.
2.4. DATA MANAGEMENT SYSTEM (DMS)
It is now common practice for an Owner to insist that the contractor collects,
presents and stores all his construction data in real time in some form of an
automated DMS (Data Management System). We have found that the
contractors are often overwhelmed (initially at least) by the needs, scale and
seriousness of such a system. This must not be permitted by the Owner to
occur: a fully compliant DMS must be up and running before production work
commences. From the technical viewpoint alone, it is integral to controlling and
analyzing the treatment in real time, and informing all interested parties on the
progress and effectiveness of the work (e.g., via Trend Analyses). It is therefore
the only true basis for determining when the work is actually complete or if further
work (e.g., higher order holes) is required, and where.
The Contractor’s DMS must be controlled by a suitably qualified grouting
engineer (not just an IT specialist). There must be a similarly-equipped,
dedicated and experienced engineer on the Owner’s side. All parties must have
simultaneous access to all the information generated during the works.
1617
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik