2. SUMMARY OF CASE HISTORIES (1975-2017)
A recent review [5] provides details of 27 major remedial cutoffs using
“excavate and replace” methods, as opposed to “mix in place” methods [6].
These projects are listed in Figure 2 which also shows the principal construction
method and Specialty Contractor. One project remains in progress (East Branch
Dam, PA), while three others are foreseen to commence in 2018, including two in
Tennessee and the second phase of Herbert Hoover Dike, FL. Details of
construction methods and cutoff material design are provided in older texts (such
as [7]), while many of the more recent case histories referred to in Figure 2 are
summarized more recently in reference [6]). Several different methods of
constructing cutoffs have been successfully and safely utilized on these projects,
including the use of clamshells, hydromills and large diameter rotary drills. The
choice of method is primarily dictated by the geotechnical conditions, the depth of
the cutoff, dam safety considerations, and the traditional preferences of the
respective Specialty Contractors.
3. LESSONS LEARNED
3.1. DESIGN CONSIDERATIONS
3.1.1 Geological and Geotechnical Site Characterization
The following observations are provided, for brevity and clarity, in bullet
form. Some readers may find certain lessons to be self-evident and not worthy of
consideration. However, each topic has its roots in situations personally
observed by the author and, in his opinion, each merits inclusion.
ď‚· Before designing a new program of investigation, very carefully reexamine
existing, historical information (e.g., grouting programs, original site
investigation data, construction photos, as-built drawings), and dam
performance data, especially “signs of distress” (sinkholes, seepages,
depressions, erratic piezometer readings, etc.). The work product is a basic
but robust hydrogeological model.
ď‚· The intensity of the new investigation must reflect the variability of the ground
conditions as interpreted from the preexisting hydrogeological model (but will
be, practically, governed by budget and access, and the project risks).
ď‚· Drill holes must extend over the entire length and depth of a foreseen cutoff.
Their location should reflect what is suspected to be the main risk areas
identified in the preexisting hydrogeological model.
1626
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik