rock mass. Water permeability tests performed in investigation drillings pointed out
important absorptions on the left slope, particularly in the tectonised area between
the granite and the breciphied shale.
3. FOUNDATION WATERTIGHTENING
In order to avoid the seepage along the discontinuities in the upper part of
the rock foundation the entire base width of the core was grouted to a depth of 6
to 12 m to form a grout platform, or a grout bulb (fig. 2). The grout curtain was
designed based on lugeon values and consists in two rows of grouting holes, with
a depth of 60 … 80 m, performed from the grouting gallery. On the right abutment,
on the dam valley and on the lower half of the left abutment the grout curtain
achieved the required technical conditions. On the upper part of the left abutment,
above the elevation 985 mASL the control drillings have shown very large water
absorptions. Areas of abnormally high or low grout takes in comparison to the
Lugeon values were identified for further analysis. The grouting records for these
abnormal zones were reviewed carefully along with the pressure testing and
grouting records from adjacent holes.
The difficulties encountered during the grouting process due to complex
geological conditions has imposed the temporary stopping of the grout curtain
performance. Consequently, the reservoir water level was severely restricted. The
apparent inability of the traditional grouting practices to provide a watertighteness
barrier of acceptable efficiency and durability led to the idea of replacing the grout
curtain with a concrete wall. The attempt was abandoned bearing in mind that the
average cost of a concrete wall is many times that of a grouted cut-off, and that
there was currently a shortfall in contractor capacity to construct the former,
After 10 years of studies and analyses it was decided to complete the grout
curtain. A campaign of high quality drilling, permeability testing and grouting was
first conducted. The decision was supported by the fact that grouting equipment,
methods and contracting procedures have evolved over the last decade and the
engineers can now design, build and verify the performance of permanent grouted
seepage barriers for dam structures.
The extension and completion of the grout curtain performed in the first stage
was differentiated according to rock mass characteristics (see fig. 2). For the schist
zone, between 960 and 1021mASL elevations, along a length of 146 m, groutings
for the bulb underneath the core foundation, 15 m deep were firstly provided. The
grout curtain itself, with a depth of 35 m, consists in three rows of grouting drillings
disposed at 0.5 m in between and 2m along the curtain. For the brecia zone, with
a length of 23.3 m, between elevations 1021 and 1028 mASL, bulb grouting and
grout curtain with a depth of 35 m encountered some anomalies. In some places
the grout take was quite large in spite of low Lugeon values. For the granitoid zone,
with a length of 150 m, between elevations 1028 and 1078.50 mASL, the grout
curtain consists in three rows of grouting drillings, with a depth of 55 m for the ones
1650
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik