4.4. PANEL ENCASEMENT WALL
The 210 m long main section of the encasement wall was excavated in 3.2
m long panels reaching depths of over 60 m (). Each primary panel was pre-
excavated using a hydraulic grab mounted on the MC 96. After pre-excavation of
the secondary panels by the onsite available BG50, the element was fully
excavated using a BC 50 hydrocutter mounted on a BAUER MC 128 foundation
crane. All excavations were performed under bentonite slurry-support. Concrete
was placed via two tremie pipes per panel.
The technical specifications (USACE 2011) [2] called for tolerances of
0.25% maximum panel verticality deviation, maximum six degrees panel rotation
(twist) and a minimum 0.15 m overlap between primary and secondary panels
throughout the full width and depth of the wall. To achieve these goals the cutter
needs to be steered, which requires both precise information about the actual
position of the tool with respect to design and steering capabilities.
5. BARRIER WALL INSTALLTION
5.1. COLUMNAR BARRIER WALL
BFC’s design consisted of twelve 1.22 m diameter primary columns up to
57.3 m deep, and eleven 1.37 m diameter secondary columns up to 56.7 M deep.
Downhole water hammers, Wassara W150 and W200, in conjunction with a
Klemm KR 806-4 drilling rig were used to drill the pilot holes. All but two pilot
holes (maximum verticality 0.35%) achieved the verticality tolerance of 0.25%.
Due to the active steering during drilling by means of a bent sub, a piece of drill
string with a slight angle to put the hammer at an angle to the borehole axis, the
maximum deviations out of plumb were observed above final depth. After final
excavation, the pilot holes were tremie-grouted with flowable fill.
BFC used rock augers and drilling buckets, both equipped with stingers
(extended pilot bits) to follow the pilot hole, to excavate the columns. Drilling was
performed dry at the top and under water at depth with the BG 50. One tremie
pipe was used to place the concrete. Geometry surveys were performed using
BAUER’s proprietary Drilling Inclination System (DIS) and the Koden and
SoniCaliper methods with the Koden data being used as as-built data set. Two
secondary elements had to be reamed to a diameter of 1.45 m to meet the 0.61 x
0.15 m overlap requirement at all investigated 1.5 m depth intervals.
1697
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik