Bedding modulus and the level of mobilization are interacting so the
bedding modulus has to be determined iteratively.
For simplifying the calculation, the bedding modulus can be assumed
constant over one soil layer, at least if the embedment depth is small [4].
Furthermore, the MIP wall may only reach down to the gravel layer in order to
establish groundwater flow windows (Figure 5).
In addition, the compressive strength of the MIP wall needs to be defined.
The compressive strength depends on the soil structure, the content of cement,
water, bentonite, etc. According to Witt [12] a characteristic compressive strength
of UCS = 5 N/mm² is a reasonable value for earth concrete structures. In DWA
(2005) [15] further case studies are mentioned applying less strong mixings with
a compressive strength from 0.3 to 1.2 N/mm².
3.8. ANALYSES
The applied software the deformation and moment curve for the indicated
system, and it determines the necessary embedment depth. Based on these
results a type of steel sheet pile can be selected which meets the requirements
for the internal stability and the development of the arching effect.
When selecting the type of the steel sheet pile the dimensions are dictated
by the width of the drilling augers, which is, e.g., 370 mm for the smallest rig of
BAUER equipment. The steel sheet piles may therefore be maximum 310 mm
wide in consideration of at least 30 mm concrete cover. Further, the distance of
each sheet pile need to be defined which may vary between 1.0 to 5.0 m in
general, mainly depending on the height of the dam (= failure height) and the
existing geotechnical conditions.
4. RESULTS
Fig. 6 shows the results of the analysis with the software of GGU, e.g. the
moments, shear forces, and the deformation along the MIP wall.
The comparison of different alternatives shows that a wall depth of 7.5 m
and a distance between the steel sheet piles of 2.7 m leads to the least amount
of steel per meter levees (Table 5). When the embedment depth is reduced or
increased, the amount of steel increases. As a result, the MIP wall does not have
to be embedded in the impermeable soil layer and the aquifer is sealed so that
the groundwater exchange is guaranteed also for normal flow conditions.
1737
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik