ď‚§ From technical aspect; watertightening with geomembrane has better
results than upstream concrete slab and brings about higher level of
certainty.
ď‚§ From time aspect; using geomembrane shorten the duration of the
project due to simultaneous construction of dam body and impermeable
system. However implementing upstream concrete slab should be done
after completion of dam body and foundation settlements.
ď‚§ From cost aspect; both concrete slab and geomembrane system have
almost had the same expenditure in this project but as mentioned
before, the shorter the time of construction, the less the costs of project.
REFERENCES
[1] PAZHOUHAB-ABFAN J.V.C.E.; Dam body design report; 2009.
[2] ACI 207.5R-11; Report on roller-compacted mass concrete; 2001.
[3] A. SCUERO & G. VASCHETTI; Three recent geomembrane project on new
RCC dams; 6th intl. symposium on RCC dams; Spain; 2012.
[4] A. LOCHU & F. DELORME & P. CARLIOZ; Design and build of Rizzanese
RCC dam; 6th intl. symposium on RCC dams; Spain; 2012.
[5] [J. P. GIROUD, M. H. GLEASON & J. G. ZORNBERG; Design of
geomembrane anchorage against wind action, Geosynthetics International;
1999.
[6] ERNEST K. SCHRADER; Chapter 20 of concreteconstruction engineering
handbook; 2008.
[7] ICOLD Bulletin No.135; Geomembrane sealing systems for dams; 2010.
1795
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik