of 31 m below the foundation level. Due to the complex geological conditions,
both the upstream and downstream slope is stabilized by surcharge
embankments. The dam is up to 800 m wide at its toe. The slope of the upstream
face is 1:2,1, while the slope of the downstream face is 1:1,75 (Fig. 2).
The bottom outlets and the hydropower plant are situated to the tower,
which is located at the deepest point of the former riverbed near the upstream toe
of the dam. The tower is 63,4 m high and its outer diameter is 20,4 m.
The access to the tower is provided by the 475 m long tunnel that connects it with
the downstream toe of the dam. The bottom half of the tunnel serves as a tailrace
tunnel from the bottom outlets and the hydropower plant.
The largest flood since the construction of the dam occurred in March 1981.
The dam attenuated the peak inflow of 650 m3.s-1, which is nearly the 1 in 50 year
flow to the outflow of approximately 550 m3.s-1, which equals 1 in 20 year flood.
3. NECHRANICE DAM MONITORING
Due to the expected significant settlement of the dam, no inspection gallery
or grouting gallery was designed. Instead, a network of geodetic surveying points,
wells and piezometers was designed for the dam monitoring. The instrumentation
comprised of a system of 82 piezometric boreholes, 53 levelling wells, 115
leveling points and lateral and 63 vertical movement monitoring points (Fig. 3).
Fig. 2: Nechranice Dam cross-section
1860
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik