0.1 m3/s. At least two other leakage points (springs) in the vicinity of the Bailey
bridge could be observed. The total discharge of all these springs was estimated
to 1.2 mÂł/s.
Obviously, the quality and/or the dimensions of the grout curtain are
responsible for the described seepage. Most likely, the seepage water bypasses
the grout curtain vertically or laterally. The curtain might be either not deep, not
long or not tight enough to prevent seepage. It could be even possible that seepage
water directly passes the grout curtain through portions of increased permeability,
using ungrouted open joints. The above statements basically concern the right
bank.
At the left bank, the seepage paths may not even touch the actual grout
curtain rather than be interrupted and stopped there. Reservoir water may seep
into the limestone rock mass outcropping directly upstream of the dam. From there
it may flow through joints and fissures, possibly also karst channels inside the rock
mass following the general trend of the bedding. In the Bailey bridge area, some
2 km away, it eventually discharges at several springs.
With respect to the events happened during impounding, two potential
problems exist. One of which pertains to the amount of seepage losses. The other
is related to the forces exerted by the seepage. Loss of water through underground
seepage may be of economic concern for the storage dam, but it will not adversely
affect the safety of the dam at Gomal Zam. Main concern of the underground
seepage is the stability of the dam and the downstream slopes.
The major purpose of the multiannual (carryover) storage reservoir is for
irrigation. The average annual flow is 16 mÂł/s. If the seepage losses exceed
1.2 mÂł/s, or 7.5% of the natural flow, the losses are considered inacceptable. They
may affect the irrigation of 66,000 ha of farmland.
7. ADDITIONAL SEALING MEASURES DURING RESERVOIR
IMPOUNDING
In order to improve the existing grout curtain and to further reduce the
permeability of the rock mass, additional grouting was carried out as immediate
measure, by utilizing existing drainage holes in EI. 634 m gallery. Aim of the
grouting was to seal big seepage passages and to control the seepage flow into
EI. 634 m galleries in order to provide normal working conditions in the gallery. In
the same time, this measure should enhance the thickness of the grout curtain and
to improve its water tightness [6].
Since the permissible uplift pressure on the dam foundation behind the grout
curtain is limited, the reactivation of the drainage system after completion of the
1900
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik