Cut-off walls, in general, are constructed beneath the earth’s surface to
control horizontal flow of groundwater and contaminants. In cut-off wall
construction in earth dam foundations, alluvium foundation materials will be
removed and the gap will be refilled by good filler material such as drilling mud,
rigid concrete or plastic concrete. Most commonly, cut-off walls are vertical and
ideally penetrate down to a very low-permeable stratum, a clay or impervious
bedrock, which forms a well-sealed base for the controlling the movement of
groundwater in dam foundation [5,6]. Because of cut-off walls being influenced by
the dam settlement due to its weight, horizontal and vertical displacement
influenced during first impounding, and specially, condition such as earthquake, it
is necessary to be designed in a way that the deformations due these conditions
be the least possible and prevent cracking in the wall. In this regard, using plastic
concrete for cut-off walls is one of the best solutions, since it has sufficient strength
and flexibility to withstand static and seismic stresses and undergo seismic
deformations along the surrounding soil [7].
In this paper, function of the plastic concrete cutoff wall in one of the zoned
embankment dams in Iran, namely Silveh Dam, is evaluated by considering
instrumentation measurements. In this regard, a performance index, k, has been
introduced to evaluate the sealing performance of the water barrier cutoff wall
system. For this purpose, related analyses have been performed on the measured
pore pressure data obtained from pore pressure gauges located beneath the dam
foundation at three different cross sections.
2. SITE AND THE DAM BODY CHARACTERISTICS
Silveh Dam is a recently constructed zoned earth dam located about 12 km
Northwest of Piranshahr city in the Western Azerbaijan Province, Iran. Feasibility
studies of dam construction on the Lavin-Chai river started in 1975 and Phase-I&
II studies and geotechnical site investigations were completed in 2006 with more
than 1353 meters of boring, by Abgeer Consulting Engineers. The studied dam
body is placed on a wide valley which comprises a coarse-grained alluvial deposits
with maximum of 65 m depth in right bank and limestone or schist rock in left bank,
underlain by a layer of lightly metamorphosed limestone and shale with lenses of
slate, metamorphic sandstones, and powdered layers of schist and mica schist.
The dam body encompasses different zones, including a clay core and an
impervious upstream blanket, upstream and downstream shells of coarse-grained
gravelly sand, drain and filter [8, 9]. The capacity of the dam reservoir, at its normal
water level (1573.5 m.a.s.l), is about 84 million cubic meters. With a crest level of
1579 m.a.s.l, the maximum height of the dam is approximately 89 meters from
foundation and its crest length is near 720 meters. The maximum height section
and the plan of the Silveh dam are shown in Fig. 2 and Fig. 3; respectively. Some
Instruments are installed in the dam body and its foundation in order to monitor the
behavior of the dam under different loadings, such as the dam body weight,
embankment construction stages, dynamic and static pressures from the reservoir,
1921
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik