weathered to weak weathered underlying bedrock. When the dam height is 100m
to 50m, it can be built on the bedrock of gently weathered and weak weathered
bedrock. When the height of the dam is less than 50m, it can be built on the middle
to the upper of the weak weathered underlying bedrock.”[3] The DL’s standards
demand that “high dams should be excavated to class II rock mass and can be
excavated locally to class III rock mass. Moderate and low dams can be loosened
properly.”[4] The developing trend of construction base selection in Chinese
standards is single weathered estimate to rock mass classification.
The USBR’s standards determine the base level according to the maximum
allowable stress in the foundation. The USACE’s standards emphasize the
application of the dam’s stress to determine whether the foundation is suitable. The
USBR’s standards provide that the maximum allowable stress in the foundation
should be less than the compressive strength of the foundation material, divided
by the safety factor 4, 2.7 and 1.3[5], which are respectively for normal, extreme
and extreme loading combinations.
The USACE’s standards require that if the deformation modulus value below
500000 pounds per square inch (3.4GPa), the reasonable value of deformation
modulus should be adopted to conduct stress analysis fully and if the stress of the
dam are within the allowable stress range in a variety of conditions, the design is
acceptable[6].
3.2.2. The treatment of weak structural plane
The USBR’s standards introduce the “dental treatment” which means that
weak planes and zones require special treatment in case of removing the weak
material and backfilling with concrete, and develop general rules for guidance as
to how deep transverse seams should be excavated. Based on foundation
conditions and stresses at Shasta and Friant Dams, the USBR’s standards have
resulted in the development of the following approximate formula for determining
the depth of dental treatment[5]:
0.002 5 150 (45.72 )
0.3 5 150 (45.72 )
d bH H feet m
d b H feet m
  
   [1]
where:
H = height of dam above general foundation level.
b = width of weak zone.
d = depth of excavation of weak zone below surface of adjoining sound rock.
(In clay gouge seams, d should not be less than 0.1 H)
These rules provide a means of approach to the question of how much
should be excavated, but final judgement must be exercised in the field during
actual excavation operations.
Chinese standards, however, just suggested that the depth of treatment can
approximately equal to 1.0-1.5 times the width of the weak zones or determined by
calculation, but didn’t give the specific computational method.
3.2.3. Cement grouting
1990
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik