Page - 2094 - in Book of Full Papers - Symposium Hydro Engineering
Image of the Page - 2094 -
Text of the Page - 2094 -
COMMISSION INTERNATIONALE
DES GRANDS BARRAGES
-------
VINGT-SIXIÈME CONGRÈS DES
GRANDS BARRAGES
Autriche, juillet 2018
-------
OBERVERMUNTWERK II: NUMERICAL MODELLING AND DESIGN
CHRISTOPHER DICH1), FRANZ TSCHUCHNIGG2)
1)Vorarlberger Illwerke AG, Bereich Produktion und Technik,
Bauprojektierung
2) Institute of Soil Mechanics, Foundation Engineering and Computational
Geotechnics, Graz University of Technology
AUSTRIA
1. INTRODUCTION
The pumped storage plant Obervermuntwerk II with an underground
powerhouse cavern is located in the western part of Austria. The construction of
the approximately 500 million € project began in May 2014 and the power plant is
expected to start operating in 2018. In the pre-designing phase 2D-FE analysis for
the powerhouse cavern were performed and during the main excavation of the
cavern, 3D finite element calculations using Plaxis 3D [1] have been conducted.
One objective of the paper is to summarize results from 3D finite element analyses
performed in order to assess the performance of the two main caverns of the hydro
power plant project. Additionally the headrace system of the power plant and its
geotechnical design is presented. Finally, also some experience gained during the
construction works is discussed.
2. PROJECT DESCRIPTION
The new pumped storage power plant (PSPP) is located parallel to the
existing Obervermuntwerk I. The average construction altitude in the powerhouse
2094
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik