To investigate the behaviour of the shotcrete lining additional 2D finite
element analyses have been performed where the three shotcrete layers of the
powerhouse cavern were modelled with an advanced constitutive model for
shotcrete taking account of tension softening (Schädlich et al. [5]). Details of these
FEA can be found in Tschuchnigg et al. [4].
5. HEADRACE SYSTEM OF OBERVERMUNTWERK II
5.1. SILVRETTA TUNNEL, PRESSURE SHAFT, MANIFOLD
The generation water system of the pumped storage works consists of a
number of plant components (see Fig. 1 and Fig. 2). In the following the headrace
tunnel called “Silvrettastollen”, the pressure shaft and the manifold including
tailrace tunnel and outlet structure are presented in detail.
The 2773m long Silvretta headrace tunnel, with a gradient of about 9%, starts
downstream of the gate chamber at chainage 184 and ends at the “Kaverne
Ausbaurohr” near chainage 2947. At chainage 2490 the headrace tunnel branches
off for the Obervermuntwerk I, which is also supplied with headwater from the
Silvretta tunnel. The connection tunnel to the Krespa surge tank is located at
chainage 2550. Up to chainage 2570 the Silvretta tunnel (with a clear internal
diameter of 6.8m) has a 30cm thick unreinforced concrete lining with invert
segments. At this chainage is the transition to the 256m long section with thin-
walled steel lining (Fig. 6). The thin walled steel lining (with a diameter of about
6m) has a thickness of 10mm. The thin steel lining is protected against external
water pressure with a support ring with a wall thickness of 0.55m. In this area, the
tunnel has an internal diameter of 4.9m. At chainage 2825 is the transition to the
thick-walled armored section (Fig. 6), where the internal diameter reduces to 4.5m.
The thickness of the steel lining varies between 44mm at the transition to the thin-
walled steel lining and 36mm at the transition to the downstream pressure shaft.
The pressure shaft is designed as an inclined shaft with a slope of 48°; the
inclined length is about 110m. The circular flow section has a thick-walled steel
lining with wall thicknesses between 32mm at the upper bend and 35mm at the
adjoining manifold. The manifold, consisting of the upstream Y-ducting with the two
main runs and the subsequent two turbine feed pipes and two pump risers, is
designed for hydraulic short circuit operation (simultaneous operation of turbines
and pumps). The water from the two machine sets in turbine operation is collected
in the tailrace tunnel and flows down to the outlet structure in the Vermunt reservoir.
In its vertical alignment, the tailrace tunnel is divided into a horizontal and a sloping
section with a constant inclination of 19.5% towards the outlet structure. The
internal diameter of the cast concrete ring is 6.4m, with a wall thickness of 0.35m.
2099
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik