Page - 2116 - in Book of Full Papers - Symposium Hydro Engineering
Image of the Page - 2116 -
Text of the Page - 2116 -
COMMISSION INTERNATIONALE
DES GRANDS BARRAGES
-------
VINGT-SIXIÈME CONGRÈS DES
GRANDS BARRAGES
Autriche, juillet 2018
-------
LINING CONCEPT TO CONTROL HYDROFRACTURING OF THE POWER
WATERWAY OF HPP QUITARACSA IN PERU
Dr Wynfrith RIEMER
Senior Engineering Geologist and Hydrogeology Expert
Michael THIEL
Senior Structural Engineer and Project Manager,
PÖYRY SCHWEIZ AG
Dr Roland SCHMIDT
Senior Hydropower Expert and Project Director,
PÖYRY (PERU) S.A.C.
PERU
SUMMARY
Engie’s 118 MW Quitaracsa hydropower project is located in the Cordillera
Blanca mountain range in Ancash/Peru, on the Quitaracsa River, a main tributary
of RÃo Santa, which is one of Peru’s mayor rivers flowing into the Pacific Ocean.
HPP Quitaracsa’s gross head is 874 m and its design flow 15 m³/s. The plant
comprises an hourly regulation reservoir of 270 000 m³ and a 5.5 km long inclined
pressure tunnel, with 16% constant slope, connecting the reservoir and intake
works with the underground powerhouse.
The entire underground structures of the project are located in granodiorite
of the Cordillera Blanca Batholith, and the original design provided for only 160 m
of steel lining, followed by 200 m of concrete lining, to protect the powerhouse
cavern against seepage inflow. However, the Cordillera Blanca Fault Zone,
tectonically active, runs in the immediate vicinity of the power cavern.
2116
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik