1.2. PURPOSE AND OBJECTIVES
This HCV replacement is one of main tasks of BBWS Citarum, and with
this paper as material information in maintenance implementation of mechanical
replacement and electrical equipment hollow cone valve on Jatiluhur/Juanda Dam.
The purpose of this paper as one example reference for other dams in replacement
maintenance of mechanical and electrical equipment hollow cone valve.
1.3. GENERAL DESCRIPTION
Jatiluhur Dam (Ir. H. Juanda) is located approximately 100 km southeast
of Jakarta, which can be reached through Jakarta-Cikampek toll road and
Cipularang toll road (Cikampek-Jatiluhur), and 60 km northwest of Bandung,
which can be reached by road toll Cipularang (Bandung-Jatiluhur). From
Purwakarta City about 9 km west. Based on geographical coordinates, main
position of Jatiluhur Dam is 6o 31' South Latitude and 107o 23' East Longitude.
This dam began built in 1957 marked with laying the first stone of development
by first Indonesia President that is Ir. Soekarno.
Jatiluhur Dam is the largest dam in Indonesia, damming Citarum River
flow in Jatiluhur District - Purwakarta District - West Java Province, forming a
reservoir with an area of ±8300 ha and around 150 km of reservoir at normal
water surface elevation ±107 m above sea level (mdpl). Total area of Jatiluhur
Dam catch is 4,500 km2. While catch area large that direct to dam after built
Saguling and Cirata Dam in upstream reaches 380 km2 which is 8% from catch
area total. The catch area (upper Citarum) covers Bandung district, West Bandung
district, Bandung city, Cimahi city, Cianjur district and Purwakarta district.
Originally designed to have a capacity of 3 billion m3, but currently only 2,685
billion m3 (bathymetry in 2013) this reduction is due to sedimentation. However
after built Saguling and Cirata Dam in Jatiluhur upstream area, sedimentation rate
is decreasing. Jatiluhur Dam is a multipurpose dam, with 6 turbines with capacity
248 m3/s and power plant with capacity 187 MW, irrigation water supply for
±240.000 ha rice field, capital city raw water, fishery cultivation and flood control
at downstream of Citarum river which managed by Perum Jasa Tirta II.
2170
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik