"THEORY OF EVERYBIM" â WORKFLOW OPTIMIZATION
HYDROPOWER NORWAY
Kristoffer S. BUGGE
Hydropower Engineer and Head of BIM Coordination - Energy Division,
NORCONSULT AS
NORWAY
1. INTRODUCTION
Traditionally, construction and hydropower projects have been designed and
built based on multiple 2D drawings. Drawings have been used since ancient
times, when they were cut into stone. Our experience with drawings is that a lot of
time is spent on unnecessary perfection of the appearance of the drawings, such
as line thickness, textures, company standards, etc. Much of this is not relevant for
building the desired construction and can be considered poor use of valuable time.
Technology is at the same time changing rapidly around us, and its growth is
almost comparable to an exponential curve (Fig.1).
This growth/development is particularly relevant in our industry, as it
represents an enormous potential that is accessible to all. We wanted to take
advantage of this potential and we had to make a major change in the way we
worked. Major changes are not easily implemented in a company or in a project
since humans by nature are reluctant to change and tend to favor established
routines. We had to challenge the established routines and get started. Our main
goal was to be the first to complete an entire project without traditional 2D drawings
at all. We wanted to deliver a fully integrated âBuilding Information Modelâ (BIM)
that was available to everyone at any time throughout the project, consisting of all
necessary geometry and information for both design and construction phase. This
leads to more constructive use of time since changes will be made on dynamic
objects rendered in an interdisciplinary model and not on many drawings with
countless references. The concept was "Paperless Design, Paperless
Construction ". No one had done this before. The whole Industry said it was too
early, even the software developers said we had to wait a couple of years before
this could be done in full scale. Someone had to take the first step.
2204
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen UniversitÀt Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik