for a couple of days, then dewatered and inspected, and put back in service. In
2014, 6 years after installation, the tunnel was again dewatered and inspected by
PG&E. The detailed inspection did not find one single damage, no repairs were
needed, and the tunnel was put back in service. Data readings have shown that
the geomembrane system is successfully dewatering the mountain and preventing
seepage that could aggravate ground movement.
3. RECENT CASE HISTORIES
3.1. HELMS HIGH-PRESSURE TUNNEL
The Helms Pumped Storage Project conduit and penstock system, owned
by PG&E, connects Courtright and Wishon reservoirs in the Sierra Nevada
Mountains of central California. The powerhouse complex is located more than 330
meters underground in granitic rock. The Helms Penstock Access Tunnel,
approximately 76 m long and > 8 m in diameter, terminating into a 10.6 m thick
concrete plug with maximum static hydrostatic pressure exceeding 5.1 MPa, has
been in operation for more than 30 years and there was a desire to reduce seepage
of high pressure water from the tunnel into the mountain. PG&E had installed a
geocomposite liner into Belden hydraulic tunnel in 2008. Helms represented an
approximately tenfold increase in pressure in respect to Belden, and more than
threefold in respect to the Thissavros tunnel cited above.
Full scale testing was undertaken to validate a preliminary design based on
anchorage with special tensioning profiles and perimeter seals conceived to resist
the high pressure. The Deep Ocean Test Facility in Maryland, where the US Navy
deep submergence vehicles were tested, was the only facility found with adequate
equipment to allow testing under the required maximum pressure of 8.52 MPa. All
components and design details of the geocomposite system (“Fig. 1”) were tested
to full dynamic pressure. The results proved a SIBELON® CNT 5050
geocomposite, a 3.5 mm geomembrane with a geotextile layer heat-bonded onto
bottom sides of the liner, and its all-stainless-steel anchorage components, would
withstand the pressures.
In the final design, the SIBELON® CNT 5050 geocomposite is anchored to
the concrete subgrade by sixteen longitudinal fastening lines consisting of
tensioning assemblies placed at appropriate spacing, and of one fastening line
consisting of flat profiles, centred at the crown of the vault. The tensioning
assemblies consists of two profiles: a first solid trapezoidal profile is fastened to
the concrete (“Fig. 2” at left), the geocomposite is laid and punctured on the
anchors fixing the first profile, and then permanently anchored by installing over it
a second profile, whose shape is such that when the two profiles are tightly
connected they achieve tensioning of the geocomposite (“Fig. 2” at right).
2233
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik