Fig. 3
Testing drainage discharge capacity at Helms high-pressure tunnel. At left,
after sealing of the geomembrane system, water present behind the liner exerts
backpressure deforming the geocomposite. At right, the pressure relief valves have
discharged the water inside the tunnel, the geocomposite is recovering the
deformation
3.2. TUNJITA SURGE CHAMBER AND SHAFT
The Tunjita scheme in Colombia includes a surge shaft, an access gallery at
the bottom of the shaft and a headrace tunnel (“Fig. 4”). All these structures are
lined with three 0.05 m thick layers of shotcrete reinforced with a steel mesh, and
with a 0.25 to 0.40 m thick layer of reinforced concrete. In 2017, an exposed
SIBELON® CNT geocomposite system has been installed as safety water barrier
on the surge chamber and shaft, and on the tunnels.
Fig. 4
The Tunjita scheme
2235
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik