The reliability test shows that the value of Cronbach’α for all the 5 sorts of
problems are larger than 0.85, indicating a good consistency for all the 5 sorts,
hence the classification is reliable. The results shown in Table 3 reveals the
following findings:
1. In general, standard management problems gets the highest score,
reaching 3.11. It shows that integrated management in standard issues is a key to
promote the ability of Chinese contractors;
2. Engineering-Procurement-Construction integrated management problems
gets a high score of 3.10. Specifically, low coordination efficiency between design,
procurement and construction gets 3.17, indicating the significance of interface
management between design, procurement and construction.
3. Design problems scored 3.06, ranked third. Moreover, we can find that low
approval rate for design and poor communication with engineers scored 3.19 and
3.17. These reveal that there is an urgent need to improve the design capability of
Chinese contractors using foreign standards.
4. Construction problems scored 2.89 with the rank of 5, showing a good
construction ability of Chinese contractors. Nevertheless, construction costs
increasing got a 3.30 score, ranking second among all. This demonstrates that cost
increasing due to unfamiliarity with the differences between Chinese and foreign
standards is a critical issue that Chinese contractors need to deal with.
4.4. PROJECT PERFORMANCE
In order to understand the performance of an international hydropower
project conducted by Chinese contractors, respondents were asked to rate the
status of 11 indexes (see Table 4).
Table 4
Performance of international hydropower projects
Performance Score Std. Rank
Safety 4.16 0.68 1
Client’s satisfaction of the contractor's service 4.16 0.75 2
Corporate-Social-Responsibility (CSR) 4.15 0.72 3
Environment protection 4.14 0.72 4
Client’s satisfaction of the product 4.11 0.72 5
Quality 4.07 0.76 6
Enhancing the brand effect 3.99 0.84 7
Occupational health 3.98 0.72 8
Time 3.82 0.88 9
Cost 3.66 0.78 10
Profitability 3.51 1.05 11
As shown in Table 4, Chinese contractors performed well in international
hydropower projects, with all scores higher than 3.50, among which safety ranked
2272
Book of Full Papers
Symposium Hydro Engineering
- Title
- Book of Full Papers
- Subtitle
- Symposium Hydro Engineering
- Author
- Gerald Zenz
- Publisher
- Verlag der Technischen Universität Graz
- Location
- Graz
- Date
- 2018
- Language
- English
- License
- CC BY-NC-ND 4.0
- ISBN
- 978-3-85125-620-8
- Size
- 20.9 x 29.6 cm
- Pages
- 2724
- Keywords
- Hydro, Engineering, Climate Changes
- Categories
- International
- Naturwissenschaften Physik
- Technik