Page - 894 - in Book of Full Papers - Symposium Hydro Engineering

Image of the Page - 894 -

Image of the Page - 894 - in Book of Full Papers - Symposium Hydro Engineering

Text of the Page - 894 -

Fig. 11 Additional Outlet Tunnel 6. CONSTRUCTION PROGRESS The construction of dam rehabilitation started on August 2017. The construction schedule is 20 months so it will be completed on March 2019. The construction is dam crest and spillway rehabilitation that cost is about 100 million baht. In the first part of the schedule, the construction is RCC block and dam crest removal. The photo of construction is shown in Figure 12. Existing Outlet Additional Tunnel Outlet 894
back to the  book Book of Full Papers - Symposium Hydro Engineering"
Book of Full Papers Symposium Hydro Engineering
Title
Book of Full Papers
Subtitle
Symposium Hydro Engineering
Author
Gerald Zenz
Publisher
Verlag der Technischen Universität Graz
Location
Graz
Date
2018
Language
English
License
CC BY-NC-ND 4.0
ISBN
978-3-85125-620-8
Size
20.9 x 29.6 cm
Pages
2724
Keywords
Hydro, Engineering, Climate Changes
Categories
International
Naturwissenschaften Physik
Technik
Web-Books
Library
Privacy
Imprint
Austria-Forum
Austria-Forum
Web-Books
Book of Full Papers